Stakeholder Mapping (Power-Interest Matrix)
A framework plotting stakeholders by power and interest to determine the best management approach for each group.
Real World
When Tesco planned to build a new distribution centre, local residents (high interest, low power) were kept informed through public consultations, while the local council (high power, high interest) was managed closely through formal planning negotiations.
Exam Focus
In application questions, explicitly state which quadrant each stakeholder falls into before recommending a management strategy.